facebook pixel
skip to Main Content

Progress Flows On

Phase 1, Segment 1 Is Now Open. Construction of the San Pedro Creek Culture Park Continues.

To accommodate the project’s underground utility work that is currently taking place, please be aware of possible lane closures and road detours if traveling downtown near the construction area. For the latest construction and traffic information, please sign up for construction email updates below or download the San Pedro Creek app on Google Play or on iTunes.

San Antonio Park

Construction on Phases 1.2, 1.3, and 2

Updates for the week of May 31, 2020

The Sundt-Davila team will complete gas and water utility tie-ins at the Houston Street bridge as CPS Energy continues pulling and splicing underground electric utilities.

Current Closures

  • Both lanes of Houston Street are closed between Laredo and Camaron streets, and the westbound lane of Houston Street is closed between Flores and Laredo streets.
    • Eastbound traffic should follow the detour signs on Santa Rosa, Dolorosa and Flores streets.
    • Westbound traffic should follow the detour signs on Flores, Travis and Santa Rosa streets.
  • The southernmost lanes and sidewalk of Dolorosa Street from Laredo Street to Plaza de Armas are closed.
  • Calder Alley between Dolorosa and West Commerce Street is permanently closed until construction is complete.
  • Graham Street and Camp Street at the creek are closed.
  • For VIA bus stop closures and route information, please call the VIA Route Information Hotline at 210-362-2020.

New and Upcoming Closures

  • Camp Street: May 18th
  • Guadalupe: June 1st (estimated)
  • Alamo: Early July  (estimated)
  • Nueva:  Mid June (estimated)
  • Substantial Completion:  February 2023

Construction Notes

  • The Sundt-Davila team will complete gas and water utility tie-ins at the Houston Street bridge as CPS Energy continues pulling and splicing underground electric utilities.
  • Crews will sandblast the walls between Commerce and Dolorosa streets.
  • Crews will fine grade and then lay asphalt on Dolorosa Street at the bridge.
  • The team will form and pour concrete for a wall footing and stem between Dolorosa and Nueva streets.
  • A subcontractor will install the planter wall stone between Dolorosa and Nueva streets.

Phase 1.3

  • Crews continue to install drilled piers between Graham Street and Cesar Chavez Boulevard.
  • CPS Energy will continue the relocation of overhead electrical lines at the Graham Street bridge.

Phase 2

  • The team will demolish various surface features of the Camp Street bridge.

For information regarding other construction projects in the downtown area, please visit the City of San Antonio’s Transportation and Capital Improvements website.

Construction Progress Photos

×Close search
Search
Get the latest on the San Pedro Creek Culture Park
Sign up for email updates
SIGN UP
I understand that subscribing to the email list means that I agree to receive emails, including updates from San Pedro Creek Culture Park. I can update my preferences and unsubscribe at any time.
close-link