facebook pixel
skip to Main Content

Progress Flows On

Phase 1, Segment 1 Is Now Open. Construction of the San Pedro Creek Culture Park Continues.

To accommodate the project’s underground utility work that is currently taking place, please be aware of possible lane closures and road detours if traveling downtown near the construction area. For the latest construction and traffic information, please sign up for construction email updates below or download the San Pedro Creek app on Google Play or on iTunes.

San Antonio Park

Construction on Phase 1.2

Updates for the week of April 12, 2020

The Sundt-Davila team will continue construction of the southern half of Dolorosa St. Bridge setting forms for the Abutments

Current Closures

  • Both lanes of Houston Street are closed between Laredo and Camaron streets, and the westbound lane of Houston Street is closed between Flores and Laredo streets.
    • Eastbound traffic should follow the detour signs on Santa Rosa, Dolorosa and Flores streets.
    • Westbound traffic should follow the detour signs on Flores, Travis and Santa Rosa streets.
  • The northern sidewalk of Commerce Street between Flores and Laredo streets is closed. The southern sidewalk remains open to pedestrian traffic.
  • The southernmost lanes and sidewalk of Dolorosa Street from Laredo Street to Plaza de Armas are closed.
  • Calder Alley between Dolorosa and West Commerce Street is permanently closed until construction is complete.
  • For VIA bus stop closures and route information, please call the VIA Route Information Hotline at 210-362-2020.

New Closures

  • Graham Street at the creek is closed.

Construction Notes

  • The Sundt-Davila team will install water wall light fixtures between Houston and Commerce streets.
  • Installation of underground utilities at the Houston Street bridge continues.
  • A subcontractor will apply stucco to adjacent creek walls.
  • Crews will install a storm water trash collection structure at the Dolorosa Street bridge.
  • The Sundt-Davila team will pour concrete for the Dolorosa Street bridge abutments.
  • Crews will set rebar to prepare for concrete pours for the channel slab under the Dolorosa Street bridge.
  • A subcontractor will install limestone veneer between Dolorosa and Nueva streets.
  • The team will pour concrete for the wall foundation between Dolorosa and Nueva streets.

Phase 1.3

  • The Sundt-Davila team will remove asphalt to prepare for pier installations at the Graham Street bridge.
  • Crews will demolish the Graham Street bridge.
  • The team will clear the channel limits between Graham Street and Cesar Chavez Blvd.

For information regarding other construction projects in the downtown area, please visit the City of San Antonio’s Transportation and Capital Improvements website.

Preparation for Phase 2

Construction & Street Closure Update

To accommodate construction of Phase 2 of the San Pedro Creek Culture Park – from Guadalupe Street to South Alamo Street – there will be various street and lane closures.

These closures will begin late March and run through the completion of Phase 2, which is tentatively scheduled at the end of 2022.

Alamo Street: POSTPONED indefinitely

Guadalupe Street: Closure starting April 6th

Camp Street: Closure starting April 13th

Construction Progress Photos

×Close search
Search
Get the latest on the San Pedro Creek Culture Park
Sign up for email updates
SIGN UP
I understand that subscribing to the email list means that I agree to receive emails, including updates from San Pedro Creek Culture Park. I can update my preferences and unsubscribe at any time.
close-link